Rail Lines-CSX-Eastern Reg. Reclaimed Water Distribution System – Phase II

Owner
City of Orlando
Engineer
General Contractor
Garney Construction
Jacking Sub Contractor
Huxted Tunneling
Pipe Size

335 feet of 54″ OD Permalok® Steel Casing

The Problem

The bores will cross four CSX railroad tracks and I-95 using Iseki microtunneling equipment in a single drive, 26 foot deep

The Solution

After installing 600 feet of the 1,620 feet 66” Permalok steel casing, Huxted made the final drive, a 350-foot run to finish this aspect of the install.